How do you calculate a sewer pipe’s fall, and what grade is required?

Grade is vertical fall divided by horizontal run. A one per cent grade equals one unit of fall for each hundred units of run, but it is not a universal design rule.

Pipe grade is the vertical fall divided by the horizontal run, expressed as a percentage. The calculation is: grade (%) = vertical fall ÷ horizontal run × 100. Use the same units for both measurements. A one per cent grade means one unit of fall for every hundred units of horizontal distance, such as ten millimetres over one metre.

The calculation is not the design

That arithmetic explains a stated grade; it does not say that one per cent is suitable for every sewer or sanitary drain. The required grade depends on the pipe size, discharge load, system arrangement, design and the applicable plumbing requirements. The Australian Building Codes Board’s drainage design material refers to minimum drain grades and fixture loading as part of a wider sizing and system design process.

A pipe that is too flat or too steep for the design may not convey waste as intended. Existing ground level, connection levels and the route through the property also constrain the fall. Do not set, alter or bury a sewer line based on an online rule of thumb. A licensed plumber or drainer should check the design, site levels and approval requirements for the particular work.

What to ask before work starts

Ask the contractor to identify the proposed start and connection levels, design grade, pipe size and how the work will be checked before backfill. If a previous line is suspected of having an incorrect fall, camera footage may help identify deposits or standing water, but the camera does not measure the design at every point. Read what a drain camera inspection can show and where it has limits.

For excavation or building work, have underground services and the actual sewer route located first. See why sewer depth varies between properties. Contact our plumbing team to discuss a drainage assessment; the compliant design must be confirmed for the site and scope.